The Effect of Defective Motor Starting Circuits on Automatic Transfer Switch and Engine Performance



Engine generator set manufacturers have long been aware of the effects of motor starting loads on overall performance. Manuals like Onan's T-009 "Selecting Onan Electric Generating Sets for Electric Motor Loads" explain in detail how to deal with motor starting circuits.
All electric motors require extra power when starting. This extra requirement is referred to as "locked rotor KVA" (kilovolt amperes) or "locked rotor amps." (It is "locked rotor" because when an electric motor is stopped it needs extra force to get moving again, and the rotating component within a motor is called a rotor.) Assuming no load is present, the amount of power needed to start a motor can be accurately estimated by comparing the motor horsepower and the NEMA code from the motor's nameplate with a chart similar to the attached Table 2 from the Onan technical manual T-009. The resultant LrKVA value is compared to available starting capabilities as in Onan's T-009 Table 4, also attached. Through this method, an appropriate engine generator set may be chosen to drive the load.

But what happens when the load changes after all the equipment is installed?


Whenever a load is applied to a generator set, the voltage instantly drops. This drop is corrected by an application of torque from the engine and electrical power from the voltage regulator (in the generator). This correction to us seems instantaneous but may actually take many cycles in the generator's reference of time. We try to size equipment so that the voltage drop doesn't exceed 30% of the unit's rated voltage. If we exceed 30%, motor contactors fall out, fuses blow, lights dim and a lot of other bad things happen.
If an unplanned load hits the system, as when a start winding fails, the 30% mark may be passed. This can throw the entire system out of sync.
A typical air conditioning compressor uses a capacitor start motor like the drawing below:

Typical Capacitor Start Motor


Let's say, for example, the start winding has a normal impedance of 100 ohms but half of the windings are shorted out of the circuit due to a breakdown in insulation. The impedance would now be 50 ohms, or half its original value. The current now required to operate this winding would have increased proportionally, right?
The start winding is engaged only long enough to get the motor up to 75% of normal speed. It is then disconnected by the centrifugal switch. But during the time it's engaged, it may draw many times more power than the motor needs at its rated speed, even under full load, because it is using this extra winding.
As the starting motor nears its rated speed, a centrifugal switch disconnects the starting winding. If the start winding is shorted or otherwise defective, it may draw many times the usual requirement. But, since the start winding is used only for a short while, if the running winding is intact, no problem may be apparent when the motor is connected to the utility. (The utility has all the power in the world. Well, at least the North American electrical grid. It is actually referred to as an infinite bus.)
The utility power will support a gross overload for a short duration without even opening a breaker because most building codes rquire only thermal breakers. This breaker has to heat up before it can open the circuit. The short time the start circuit is used may not allow the breaker to trip. However, when a gross overload hits a generator, excessive voltage drop may occur.
Most generators use a "volts per hertz" type voltage regulator. This means as the engine slows down with load and the hertz, or frequency, drops, the voltage regulator will allow the voltage to fall off in order for the engine to get a chance to catch up with the extra load. This voltage drop may be significant.
An automatic transfer switch is designed to provide power to the load from any available source. It, therefore, monitors both the normal and emergency sources. If, when it transfers tot he emergency source, is senses a significant voltage drop in that source, and the normal source is still available, it will immediately attempt to retransfer back to normal. That retransfer action removes the load from the generator. When the overload is removed from the generator its voltage instantly returns to the normal level. The transfer switch will sense the restored voltage and again issue a command to transfer to emergency. The transfer to emergency will once again result in a severe voltage drop due to the gross overload and the cycle will repeat. This may continue until a technician intercedes or a safety device removes the overload from the circuit.
If the utility voltage is not available, the transfer switch will not cycle back to normal. Under this condition, when an overload is applied to the generator, the engine may slow down, or the voltage may drop off to unusable levels, the voltage regulator may be damaged or one of its protection circuits may open up.
All the while the generator and automatic transfer switch are trying to figure out what to do with the overload, the engine's governor is trying to handle load that is first applied, then removed, then applied again. Each smaller system within the overall emergency power system needs time, in milliseconds, to react to changing conditions. It is not uncommon for an undesirable harmonic to develop between two (or more!) systems, resulting in cycling, surging, or even mechanical failure.
When overload is suspected, it is best to test with an ammeter capable of holding a peak reading. Each suspect circuit, downstream from the automatic transfer switch, should be examined.
The example I used of a capacitor start motor is common in that most air conditioning compressors use this type of motor. However, there are many other motor starting circuits possible as well as other devices prone to failure. All circuits should be checked under both peak load and starting conditions.

Home
Back to Lester's Science Corner

1